Schipferhof 2027
Future orientation of the farm "Schipferhof" in Wollishofen
Process phases
-
12023-01-01 - 2023-05-31
Introduction
Vorbereitung Mitwirkungsprozess
Erarbeitung Rahmenbedingungen
Definiton Akteure in Wollishofen
Zusammenstellung Spurgruppe
-
22023-07-04 - 2023-11-18
Arbeit Spurgruppe
The track group consists of 15 representatives of active organisations, associations and groups from the Wollishofen district.
Tasks of thetrack group
: constructive, critical support of the- project team , assistance in the
- preparation and implementation of the public participation event,
- support in the promotion of the event
-
32023-11-18
Public participation event
At the public large group workshop, the neighbourhood population is invited to express their wishes for the future Schipferhof. In table groups, the participants discuss their ideas and requirements for the future neighbourhood uses that are to take place at the Schipferhof.
At the same time, those present can also make known how much they would like to get involved on the farm themselves in the future.
-
42023-11-19 - 2024-05-31
Work Spurgruppe (continued)
Assistance in processing the results of theparticipation event
Participation in the definition of the next steps
-
52024-03-26
Public information event
The results of the participation process so far will be presented. It is shown how these are incorporated into further work. The neighbourhood population has the opportunity to comment on
and how the
the status of the workneighbourhood population will be involved in the next development steps.
-
62024-04-01 - 2024-09-30
Preliminary work for lease tender and feasibility study construction project
Working GSZ internally
-
72024-09-25 - 2025-05-31
Lease tender Schipferhof
The Schipferhof is put out to public tender for management.
A pre-selection will be made from the applications.
The selected applicants will be given the opportunity to submit a detailed operating concept.
The concepts are assessed and evaluated according to uniform criteria. This also includes the requirements from the neighbourhood.
An internal GSZ jury will then decide on the allocation of the lease.
-
82024-10-01 - 2025-06-30
Schipferhof feasibility study
Preparation of feasibility construction project "Repair and expansion Schipferhof"