Dunkelhölzli
Monitoring Dunkelhölzli
Process phases
-
12024-07-01 - 2025-06-30
Introduction
Quantitative and qualitative surveys regarding the perception and use of the Dunkelhölzli area.
- Recording of the frequencies of visitors on the site
- User survey
- Expert interviews
-
22025-01-05 - 2026-04-30
Construction
Construction and conversion of:
- Five garden fields
- New paths, opening of streams and flood protection
- Renovation of greenhouses and surroundings
-
32026-04-01 - 2026-10-31
Survey of pilot operation
Quantitative and qualitative surveys regarding changes in perception and use of the Dunkelhölzli site during the pilot operation.
- Recording of the frequencies of visitors on the site
- Observations User
- survey
- Expert interviews
-
42027-04-01 - 2027-10-31
Survey of regular operation
Quantitative and qualitative surveys regarding the perception and use of the Dunkelhölzli area during regular operation.
- Recording of the frequencies of visitors on the site
- Observations User
- survey
- Expert interviews
-
52027-11-01 - 2028-03-31
Evaluation and final report
The findings gained from the monitoring are continuously incorporated into regular operations and also serve Grün Stadt Zürich in the planning and implementation of similar projects.